There has been so much progress! It's hard to believe that it's only been 11 days since we broke ground on October 9, 2012. Things really do move quickly after the ground breaking.
Day 4 | 10-12-12 | Poured Basement Walls
Joe did not have a chance to drive out to take pictures this day. The basement walls were poured though. Our PM called for our weekly update. He said they would be wrapping the basement on 16th, deliveries for supplies should start on the 19th and framing is expected to start on the 26th.
Day 5 | 10-13-2012 | Basement Walls & Steel Beams
Joe drove out after work. The basement walls had been poured and the frames were removed. He also saw a delivery of the steel beams.
Joe was standing at the front of the house when he took this one. The front porch is directly in front with the soon to be finished basement behind it. The garage is off to the left with the unfinished part of the basement behind it.
The orange spray paint marks are for the waterproofing. That's how far up the wrapping comes.
I think these are the pipes for the sump pump?
Day 8 | 10-16-2012 | Basement wrapped
After Joe got off of work, he drove out to see the progress. It's looking great so far!
Day 10 | 10-18-2012 | Deliveries Have Started!
Joe decided to drive by the house to see if they had done anything while waiting for the deliveries to start. Look at what he saw....
Our front door, sliding glass door, and windows have been delivered! Our front door will be black, which reminds me, I need to update our selections page.
I couldn't see it in the first photo that Joe sent to me (the one above), but we have wood too. It doesn't look like very much. Maybe there's more hiding behind it or another delivery is scheduled?
This guy was there delivering our shower/tubs. I can't wait to use city water again!
Day 11 | 10-19-2012 | Weekly PM Call
Our PM called for our weekly update. He said that we're scheduled to start the framing on the 24th or the 25th. He said that puts us about 2 weeks ahead of schedule right now. Of course that could all change, depending the the weather.
So, that's where we're at right now. I'm so excited and happy with how fast things are moving! My fingers are crossed that the weather stays nice long enough for them to finish all of the outside work.